An escape room company leased an empty retail suite in Orange Beach and needed it split into game rooms, a control room and hallways. We built it out from a bare shell in about four weeks.
Project at a glance
- Location: Orange Beach, AL
- Space: second-floor retail suite, delivered as an empty shell
- Scope: 11-foot metal stud partitions, drywall, ceilings, doors, electrical, low-voltage pathways, paint and blocking for the tenant’s room builds
- Life safety: sprinkler heads and fire alarm devices relocated for the new rooms, emergency lights, a fire strobe and panic bars on two exterior doors
- Also done: lighting, electrical and paint in the tenant’s existing suite next door
- On site: mid-April to early May 2026
- Managed by: one dedicated Wise Builders project manager, start to finish
Before: an empty shell
The suite was one open room with a concrete floor and an open ceiling.

Framing the rooms
Metal stud walls went up 11 feet to divide the suite. Wood blocking went into the walls wherever the tenant planned to hang props and game pieces.


Sprinklers, fire alarm and exits
New walls change how sprinklers and alarms cover a space. Sprinkler heads and fire alarm devices were moved to suit the new rooms. We added seven emergency lights, a fire strobe and panic bars on the two exterior doors, with a life safety plan drawn by an architect.
Drywall, ceilings and paint
Drywall was hung and finished, then each room got its own ceiling and paint colors from the tenant’s plan.


The finished rooms
We handed over finished rooms, ready for the tenant to build their games inside.




Open for business
Here are the same rooms a few weeks later, with the tenant’s games built inside them.




Planning a commercial build-out?
We build out retail, office and restaurant space across Baldwin and Mobile counties. See retail build-outs or request a walkthrough and estimate.